PARRAMATTA MEDIUM DENSITY RE-DEVELOPMENT
CHALLENGE
Prior environmental reports by others identified Acid Sulfate Soil (ASS) at the site. They advised that approx. 30,000m3 of ASS needed to be excavated, treated & disposed to allow for basement parking
SOLUTION
TRACE determined that the results provided were not consistent with ASS & proved this to the appointed site auditor through an alternative thorough testing regime. TRACE determined no ASS at the site, delivering a $13.4M saving to the developer.
RESULT
TRACE saved the project approx. $15-20M in reduced soil treatment & remediation